1. |
20-Mar-2024 09:00 AM |
19-Apr-2024 02:00 PM |
19-Apr-2024 04:00 PM |
[Installation, Testing, Commissioning of 33 KV VCB, CT, PT, Isolator, L.A. and Transformer Control Panel at different Sub Station under E.U.D.D, Rambagh, Naini, Kalyani Devi and Karelabagh, Prayagraj]
[53/SE/EUDC-I-Pra/2023-24][2024_PVVNV_919300_1]
|
Purvanchal Vidyut Vitran Nigam Limited Varanasi
|
2. |
23-Jan-2024 05:00 PM |
19-Apr-2024 02:00 PM |
20-Apr-2024 05:00 PM |
[118/EDC(H)/2023-24 ]
[118/EDC(H)/2023-24][2024_MVVNL_884322_1]
|
Madhyanchal Vidyut Vitran Nigam Ltd||C E - LUCKNOW ZONE||S E - Hardoi
|
3. |
02-Feb-2024 03:00 PM |
19-Apr-2024 02:00 PM |
20-Apr-2024 05:00 PM |
[64/EDC(H)/2023-24]
[64/EDC(H)/2023-24][2023_MVVNL_854569_5]
|
Madhyanchal Vidyut Vitran Nigam Ltd||C E - LUCKNOW ZONE||S E - Hardoi
|
4. |
06-Apr-2024 09:00 AM |
19-Apr-2024 02:00 PM |
20-Apr-2024 04:00 PM |
[Increasing electric load from 2000 KVA to 6000 KVA HV-2 M/S Best Corp Science Pvt. Ltd. Gajraula Under EDD-I Gajraula.]
[T-128/2023-24/EDCA][2024_PVVNL_921576_1]
|
Paschimanchal Vidyut Vitran Nigam Ltd.
|
5. |
18-Jan-2024 02:00 PM |
19-Apr-2024 02:00 PM |
20-Apr-2024 05:00 PM |
[102/EDC(H)/2023-24 ]
[102/EDC(H)/2023-24][2024_MVVNL_882219_1]
|
Madhyanchal Vidyut Vitran Nigam Ltd||C E - LUCKNOW ZONE||S E - Hardoi
|
6. |
04-Apr-2024 10:00 AM |
19-Apr-2024 02:00 PM |
20-Apr-2024 04:00 PM |
[Civil Maintenance and Repair works of Tower Type-V (05 Storey, Total 10 Nos. residences), Tower Type-IV- Block A and B and Tower Type-III- Block A and B (40 Nos. of residences in each Tower of 10 Storey, Total 160 Nos. of residences) at Harduaganj Th]
[ETENDER No. ET 01/ECMC/ECMD-I/HTPS/2024-25][2024_RVUNL_921228_1]
|
UP Rajya Vidyut Utpadan Nigam Ltd||Harduaganj Thermal Power Project- UPRVUNL- Aligarh
|
7. |
04-Apr-2024 02:00 PM |
19-Apr-2024 02:00 PM |
19-Apr-2024 05:00 PM |
[Increasing Capacity of Substaion]
[20/ECWD/MRT/2023-24][2024_PVVNL_921287_1]
|
Paschimanchal Vidyut Vitran Nigam Ltd.
|
8. |
16-Mar-2024 02:00 PM |
19-Apr-2024 02:00 PM |
19-Apr-2024 02:00 PM |
[Nagar Panchayat Budhana Ki Mahindra Bolero ko Antim Yatra Vahan Me Badalvaye Jane Ka Karya]
[1610/NPB/2023-24][2024_DOLBU_918684_1]
|
Directorate of Local Bodies UP||Nagar Panchayat Budhana Muzaffarnagar
|
9. |
05-Apr-2024 01:00 PM |
19-Apr-2024 02:00 PM |
19-Apr-2024 05:00 PM |
[Construction of 33 KV Line]
[24/ECWD/MRT/2023-24][2024_PVVNL_921465_1]
|
Paschimanchal Vidyut Vitran Nigam Ltd.
|
10. |
05-Apr-2024 01:00 PM |
19-Apr-2024 02:00 PM |
19-Apr-2024 05:00 PM |
[Construction of 33 KV Line ]
[23/ECWD/MRT/2023-24][2024_PVVNL_921464_1]
|
Paschimanchal Vidyut Vitran Nigam Ltd.
|